Black Koles · Journal · No. 37 · 6 min read

How does a post-production schedule work, and what does it need from you?

No. 37The short answer

A post-production schedule is a dated plan that takes footage from the shoot to finished files. It’s built backward from the delivery date, and it lists each stage, each review window and who has the ball on each day. At Black Koles the client’s deadlines sit on the same schedule as ours, because the delivery date depends on both. What it needs from you is one voice, notes on time, and decisions.

01

What are the stages of post-production?

Post-production runs in stages, and the order matters. Everything before picture lock is about the story. Everything after it is finishing.

Assembly. The editor lays the selected footage out in story order. It’s an internal step, and you usually don’t see it.

Rough cut. The first version you review. The structure is there. The color is temporary, the sound isn’t designed, the music may be a placeholder and the titles are stand-ins. This is the round for big notes: story, order, length, what’s missing.

Fine cut. The edit after your notes are in. Shots are trimmed, pacing is set, the music choice is close. Notes get smaller here: this line, that shot, a beat too long.

Picture lock. The edit is approved and frozen. No shot changes length or position after this point, because everything downstream is built to the exact frame.

Color. The colorist grades the locked picture so every shot matches and the film has its look.

Sound mix. Dialogue, music, sound design and voiceover are cleaned, balanced and mastered for where the film will play.

Graphics. Titles, lower thirds, supers, end cards and any motion graphics are finished and placed. Design often starts earlier. The final versions go onto the locked picture.

Versioning. The finished film is exported in every length, aspect ratio and text version on the deliverables list, and each file is checked.

Delivery. Final files go to you, named and organized to your specs, and the project is backed up.

02

How is a post-production schedule built?

It’s built backward from the final delivery date. We start with the day you need files in hand and work back through delivery, versioning, finishing, picture lock, each review round and the first cut. That tells us when the edit has to start, and whether the date holds.

Three things have to exist before we build it: a signed scope, an agreed editor plan and a delivery date. Without those, a schedule is a guess.

Then the fixed points go in. Your review windows have a set length in business days, written on the schedule. The number of revision rounds per asset comes from the estimate. Time off on either side is entered as a blackout, so a review doesn’t land on a week when your approver is away. A date we’ve already given you in writing stays where it is, and the internal plan bends around it.

What you get is a table with three columns: the date, what happens, and who has the ball. Some stretches will say there’s nothing on your plate. That’s build time.

On The Sect’s anthem and brand refresh, we locked the schedule before we shot. Every asset had a date, a channel and a job, from the first pillar film in the run-up to the last member spotlight in January. The whole calendar is laid out on its case study.

The Sect, Anthem & Brand Refresh
The Sect / Anthem & Brand RefreshSee the case study
03

What do you see at each stage, and what do we need from you?

You see the work at the review points, and each one asks for something specific. Assembly and versioning happen on our side.

Stage What you see What we need from you
Rough cut Story and structure, temp finish Big notes, one set
Fine cut Tightened edit, near-final music Small notes, then approval
Picture lock The approved edit A written yes
Color and sound mix Graded, mixed film Look and level notes only
Graphics Titles and supers in place Spelling, legal, logo check
Delivery Final files, every version Confirm receipt, quick check

Every cut we send comes with a note that says what state it’s in, so nobody spends a review round on temporary color.

04

Why do late notes move the delivery date?

Late notes move delivery day for day, because the schedule has no idle days in it. If notes are due Tuesday and arrive Thursday, the editor starts on Thursday, and everyone after the editor starts later by the same amount.

The colorist, the mixer and the motion designer are booked for specific days, and when the edit slides past their window, the next opening may be further out than the delay itself.

If you can see a review is going to be late, tell us before it is. We can often reorder work around a gap we know about. A surprise is harder.

05

Why do heroes lead and cutdowns follow one round behind?

Heroes lead and cutdowns follow one round behind so that decisions made on the hero film are made once. A cutdown inherits the hero’s story, music and look.

If you reviewed them together, every note on the hero would have to be repeated across each short cut. Staggered, the cutdowns are built from a hero that has already had your notes, so they arrive closer to done. And you’re never reviewing two tracks on the same day.

Welcome to Gregory shows the shape: a 1:30 hero film, cut down to a :30 and a :15, plus a :30 each for the Rhune and Arrio packs, in vertical, 4×5, square and widescreen. All five play on its case study.

Gregory, Welcome to Gregory
Gregory / Welcome to GregorySee the case study
06

What does picture lock mean for changes?

Picture lock means the edit is finished, and a change after it is a change to the scope. Color, the mix, the graphics and every export are built on the locked cut.

Move one shot after lock and each of those steps has to be reopened, in the hero and in every cutdown made from it. That’s added days, and added days go on a change order with a new delivery date. We’ll tell you what a change costs before we make it.

So treat lock as the real deadline for opinions. Make sure everyone who has a say, including legal and the person with final approval, has seen the film before you give the written yes.

07

What does the schedule need from you?

Three things hold a post schedule together.

  1. One voice. Collect everyone’s notes on your side and send one consolidated set through one person. Two sets of notes that disagree stop the edit until someone picks.
  2. On time. The review window is part of the schedule, the same as an edit day. The faster we get notes, the faster the next version turns.
  3. Decisions. “Cut the second interview line” is a note. “Could we see it a few ways” is a request for more versions, and it uses a round without settling anything. If you’re torn, tell us the problem and we’ll propose one fix.
08In practice

How Black Koles does it.

At Black Koles, every project gets a post schedule once the scope is signed, with your review dates on it next to ours. Behind it we keep a tracker with the latest link for every asset and who has the ball, so nobody reviews an old version. Delivery isn’t the last row. We back up the finals the day we deliver them and again to a second drive, and we close out the job’s actual costs against the signed estimate.

The case study to see next is Force of Nature’s It’s Just Better, because it’s the shape this schedule is built for: the 60-second film leads, and the :30 and the four :15s, one for each storyline, follow. All of them play on its page. Who you’d be working with is on our About page.